The Systems Life Cycle: Testing (Cambridge International IGCSE ICT)
What is the system life cycle?
-
The system life cycle is a structured process that guides the planning, creation, testing, and **deployment **of an information system
-
Ensures systems are** systematically developed**, meeting needs of stakeholders, minimising risks and maximising efficiency
-
The third stage is testing, the purpose is to:
- Verify that the system meets all requirements, functions correctly, and is free of bugs through various testing methods.
Test Strategies
What are test strategies?
- A test strategy is **a method of testing a completed system **to ensure all parts work as intended
- Systems are designed in a modular format
- Each module needs to be** tested independently**
- Testing is done again once all modules are joined together
- The results of testing may indicate changes need to be made, testing is repeated once all changes have been made
Test designs
| Test design | Why? |
|---|---|
| Data structures | Test all data is stored correctly |
| File structures | Test all data is stored in the correct format |
| Input formats | Test that data can be entered correctly |
| Output formats | Tests that screen output and reports are in the correct format |
| Validation routines | Tests that the system rejects unreasonable data being inputted |
Test plans
-
A test plan is designed and implemented to ensure thorough testing of a system, it includes:
- Test data: specific data used for testing purposes
- Expected outcomes: predicted results based on test data
- Actual outcomes: results obtained from testing
- Remedial action: steps taken to fix identified issues
Test Data
What is test data?
-
Test data is specific data used for testing purposes
-
There are four main categories of test data that would be used whilst performing final testing on a system
- Normal
- Extreme
- Abnormal
- Live
Normal data
- Normal test data is data that should be accepted in the system
- Normal data has a known outcome
Extreme data
- Extreme data is data that is on the limits of what is acceptable
Abnormal data
- Abnormal data is data outside of the limits of what is acceptable
- Abnormal data should be rejected by the system
Live data
- Live data is data from the old system used on the new system
- Live data has known outcomes, so it can be compared to the new system to ensure the new system works
Worked Example The European Space Agency (ESA) is building a new space telescope to orbit the Earth and search for distant galaxies. The ESA is using computer controlled robots to build the lens of the telescope. A new computer system will operate the space telescope; the new computer system is made up of several modules.
Describe how the new computer system is to be tested before it is fully operational.
[4]
Answer
four of:
Final answer: Each module has to be tested independently to ensure it functions correctly [1] Modules need to be tested together [1] Data needs to be transferred from module to module to check for data clashes [1] Errors need to be noted and corrections made [1] Then tested again [1] The system as a whole needs to be fully tested under controlled conditions [1]