Flexible Budgets (Cambridge International A-Level Accounting)
Spec point — the benefits of flexible budgeting over fixed budgeting how to prepare a flexible budget statement
Flexible Budgets
What are flexible budgets?
-
Fixed budgets do not change even if the actual figures are different
-
When the actual units sold and produced are different from the budgeted units, then a flexible budget is needed
-
There is no value in comparing the actual results to the budgeted results when the level of units is different
-
In a flexed budget, the key budgeting information will reflect the actual output
-
This is particularly relevant when preparing variance analysis
- This is used in standard costing
-
It is more meaningful for managers to use a flexible budget as a means of comparison to the actual data
How to prepare a flexible budget?
-
STEP 1 Change the budgeted revenue to match the actual units:
- Budgeted revenue ÷ budgeted units × actual units
-
STEP 2 Change the budgeted direct material to match the actual units:
- Budgeted direct material ÷ budgeted units × actual units
-
STEP 3 Change the budgeted direct labour to match the actual units:
- Budgeted direct labour÷ budgeted units × actual units
-
STEP 4 Change the budgeted fixed overheads to match the actual units:
- Budgeted fixed overheads ÷ budgeted units × actual units
Worked Example Laptop limited make and sell laptops. Here is the information regarding the fixed budget and actual results for one month:
Fixed budget Actual results Production and sales (units) 20 000 28 000 Sales revenue $ 9 000 000 11 200 000 Direct material $ 2 400 000 3 920 000 Direct labour $ 2 000 000 1 960 000 Fixed overheads $ 1 000 000 1 260 000 Total cost 5 400 000 7 140 000 Total profit 3 600 000 4 060 000 Prepare the flexible budgeted statement based on the information provided
Answer
- Change the budgeted revenue
($9 000 000 ÷ 20 000) × 28 000 = $12 600 000
- Change the budgeted direct material
($2 400 000 ÷ 20 000) × 28 000 = $3 360 000
- Change the budgeted direct labour
($2 000 000 ÷ 20 000) × 28 000 = $2 800 000
- Change the budgeted fixed overheads
($1 000 000 ÷ 20 000) × 28 000 = $1 400 000
Flexible budget
$Revenue 12 600 000 Direct material 3 360 000 Direct labour 2 800 000 Fixed overhead 1 400 000 Total cost 7 560 000 Total profit 5 040 000